1st Street Retaining Wall Project

Start: Monday, May 2, 2016

End: around the end of May, 2016

Last Updated: October 4, 2017

Project Description:

The City of Courtenay is continuing the Retaining Wall Construction Project in the 900 – 1000 block of 1st Street (1st Street Hill). 

Work is scheduled to begin Monday May 2, 2016, and is planned to be completed by the end of May. In order to safely perform the work, the road is required to be closed to all traffic including cyclist and pedestrians on Monday May 2nd to Wednesday May 4th, 2016 while the contractor is on site.

During construction, access to properties in the work area will be limited  at times. The contractor will work with residents to accommodate any access or construction related matters affected by the project, including regular garbage and recycling pickup. The contractor will make every attempt to notify residences in advance of any access and parking matters affecting individual properties.

 

Project Status:

Current