OCP Project Scope and Timeline

What is the Official Community Plan update scope and timeline?

The OCP update will occur through five phases, generally and approximately described here. For a full description of the project scope, view the Official Community Plan Request for Proposals [PDF - 214 KB]

Dialog Design and Sustainable Solutions Group will be providing consulting services for the duration of the project.

Phase 1 (August – December, 2019)

  • Initiation
  • Work planning
  • Background research and review

Phase 2 (January – June 2020)

  • Technical analysis
  • Planning model development

Phase 3 (May-June 2020)

  • Detailed Community Consultation

Phase 4 (July – December 2020)

  • Policy draft and review
  • Community consultation

Phase 5 (December – February 2021)

  • Plan delivery
  • Council presentation and Bylaw adoption