Sandpiper Drive-Millard Road Watermain Upgrade Project

Start: July 2021

End: October 2021

Last Updated: July 4, 2022

Project Description:

Contractors working on behalf of the City of Courtenay have completed the construction contract and have installed an upgraded watermain and fire hydrants along Millard Road and Sandpiper Drive. The work was completed in October 2021, and was delivered on time and on budget.

The project is now in the one year maintenance period which will end in October 2022. The contractor may be on site to correct any deficiencies or warranty items that arise before the end of the maintenance period.   

If you have any questions in regards to this project, kindly contact Brandon Donais, Engineering Technologist, City of Courtenay at (250) 703-4838 or email engineering@courtenay.ca .

Project Status:

Maintenance Period